Construction of Wynn Al Marjan Island continues at an impressive pace, with the tower now rising to its 70th floor and nearing its full 305-meter height. The resort remains on schedule for its spring 2027 opening, supported by rapid façade installation, advanced interior fit-outs, and the unveiling of new hospitality and events spaces.

Key Highlights:

Major Construction Milestones

  • Tower reaches the 70th floor, approaching its planned 305-meter height.
  • Topping-out expected by late November 2025.
  • 73% of façade panels have been installed across the tower.
  • 97% of concrete and steel work for low-rise buildings is complete.
  • Structural work for accommodations is 99.7% finished.
  • Interior fit-outs progressing at approximately 98% completion.

New Event Venue Unveiled

  • Introduction of Coral Court, a 7,700 sqm celebrations center.
  • Features include:
    • A column-free Grand Ballroom
    • Dedicated bridal and groom salons
    • Prayer rooms
    • Six conference rooms
    • An event lawn overlooking the Arabian Gulf

Dining & Entertainment Highlights

  • Wynn reveals part of its 22-venue culinary and entertainment lineup.
  • Includes:
    • Alain Ducasse’s French-American steakhouse
    • Delilah — the iconic supper club from Wynn Las Vegas and The h.wood Group

Resort Scale & Offerings

  • Wynn Al Marjan Island spans over 60 hectares.
  • Will feature:
    • 297 Enclave suites
    • 1,217 luxurious resort rooms
  • Positioned to become one of the region’s most distinctive integrated resort destinations.

Opening Timeline

  • Resort remains on track for its spring 2027 debut.