Azizi Central in Al Furjan Nears Completion, Set for Q4 2025 Handover

Monday, 14 July 2025

Azizi Developments has confirmed that Azizi Central, a premium residential project in Al Furjan, Dubai, is 57% complete and on track for handover in Q4 2025. The mid-rise building offers a mix of 1, 2, and 3-bedroom apartments, with modern amenities, lush landscaping, and lifestyle conveniences for residents.

Key Highlights:

  • Project Status: 57% construction complete; handover scheduled for Q4 2025
  • Location: Al Furjan, a fast-growing residential hub in Dubai
  • Unit Types: 1, 2, and 3-bedroom contemporary apartments
  • Amenities Include:
    • Landscaped walkways
    • Separate adult and kids’ pools
    • Fully equipped gym
    • BBQ area and outdoor seating
    • Retail and dining outlets
    • Ample parking
  • Construction Progress:
    • Structure: 100% complete
    • Blockwork: 97%
    • Internal plastering: 95%
    • Tiling: 18%
    • HVAC: 64%
    • MEP: 53%
    • Façade works: 50%
    • Finishes: 37%
    • Elevator installation: 22%
    • 414 workers deployed on site
  • Developer Quote:
    • Farhad Azizi (CEO): “Azizi Central embodies elevated, connected living and is progressing steadily to welcome homeowners by year-end.”