Azizi’s Riviera Beachfront I Nears Completion With 94% Progress in Meydan

Wednesday, 10 December 2025

Azizi Developments confirms remarkable progress on its Riviera Beachfront I project in MBR City, with 94% of construction completed. The premium lagoon-facing community is on schedule for delivery by the end of 2025, offering 555 modern homes and extensive lifestyle amenities.

Key Highlights:

  • 94% construction progress achieved on Riviera Beachfront I in Meydan.
  • Located within Azizi Riviera, a French Mediterranean-inspired waterfront community.
  • Development includes three 20-storey towers with 555 units: studios, 1- and 2-bedroom apartments, plus retail spaces.
  • Positioned along Azizi’s 2.7 km swimmable crystal lagoon with direct beach access.
  • Amenities include swimming pools, gyms, landscaped areas, BBQ zones, kids’ play areas, game rooms, and yoga spaces.
  • Structural works, blockwork, and plastering fully completed.
  • Major progress across systems:
    • Tiling & HVAC: 98%
    • MEP Works: 94%
    • Façade Works: 96%
    • Elevators: 95%
    • Finishes: 90%
    • External Works: 75%
    • Swimming Pools: 90%
  • Project backed by a dedicated 2,700-person workforce.
  • Scheduled for on-time completion by year-end 2025.
  • CEO Farhad Azizi emphasizes commitment to modern design, livability, and long-term value.